Context

Synchronous request/response communication across the IT/OT boundary introduces tight coupling between zones.

Under network partition or remote outages, synchronous mechanisms cause producers to block or fail.

BSFG must allow zones to continue operating independently.

Decision

Cross-boundary communication occurs exclusively via asynchronous replay.

Replication loops:

StoreBuffer -> ForwardBuffer

operate independently of application execution.

The network boundary acts only as a transport path; durability is guaranteed before transmission.

Consequences

Benefits:

Tradeoffs: